Oops! Something went wrong while submitting the form
Updates
Keep up with all of the For Austin updates & changes.
Closed with TOPO and break ground
Closed with TOPO and ready to break ground. Launching our For Austin campaign to raise the final $1.5m to make the move
Oct 2024
Approved Site Plan
Have approved site development permit, unanimous approval from Leander City Council for tree removal.
Sep 2024
Started TOPO Relationship
Entered relationship with TOPO to build a multi-use, 10 building, 140K sq ft space to benefit the community and house our future home.
Mar 2023
Permit Approvals
After completing a term sheet with bank, city approval, building permit, & architectural plans, the project stalled during Covid. See our FAQ page for a more detailed description.
Mar 2020
Purchased Land
Purchased 14 acres across from Rouse High School on Crystal Falls.