March Update: Slabs are Being Poured

Exciting progress is underway! The construction crew is making steady strides, averaging one to two slab pours per week. By mid-April, all slabs will be in place, and by mid-May, tilt-wall panels will be poured, bringing our future home to life!

Watch the latest For Austin Update to see the progress and discover ways to get involved!

Mar 2025

February Update: Exciting Progress on Crystal Falls!

Big things are happening at the site of our future home on Crystal Falls! From site grading and stormwater nearing completion to concrete piers being set for multiple buildings, the momentum is real. Plus, we’re finalizing designs and talking with contractors to bring this vision to life.  Watch the video for all the details and how you can get involved!  The future is bright, and we can’t wait to call this place home!

Feb 2025

December Update: Together, We’ve Unlocked the Future!

This past Sunday, we celebrated God’s faithfulness through the incredible generosity of Northpoint at our Reveal Sunday. Our goal was to raise $1.5 million over the next 18 months to make the move into our new home—a big step forward for our mission to be For Austin. Today, we’re thrilled to share that we’ve surpassed that goal, with commitments totaling just over $1.9 million! How amazing is that? We’re thanking God for what He’s done through each of you and the bright future ahead. Additional funds realized beyond our goal will likely be directed toward furnishings, fixtures, and equipment (FFE), as well as creating financial margin to steward our new home wisely. This is a moment to celebrate and look forward with anticipation—thank you for being part of this journey! Let’s keep trusting God as He continues to move in and through us.

Dec 2024

This Sunday, December 8th, is Reveal Sunday

Sunday, December 8th, 2024: A powerful moment for us to come together, share what we’ve prayed over, and celebrate the commitments God has led us to make for Austin. Together, we’ll see what our church family has pledged over the next 18 months to shape the future!

Dec 2024

We Officially Broke Ground!

It's official! If you drive by our property on Crystal Falls, you'll notice it looks radically different as site preparation and excavation has begun.

Nov 2024

Closed with TOPO and break ground

Closed with TOPO and ready to break ground. Launching our For Austin campaign to raise the final $1.5m to make the move

Oct 2024

Approved Site Plan

Have approved site development permit, unanimous approval from Leander City Council for tree removal.

Sep 2024

Started TOPO Relationship

Entered relationship with TOPO to build a multi-use, 10 building, 140K sq ft space to benefit the community and house our future home.

Mar 2023

Permit Approvals

After completing a term sheet with bank, city approval, building permit, & architectural plans, the project stalled during Covid. See our FAQ page for a more detailed description.

Mar 2020

Purchased Land

Purchased 14 acres across from Rouse High School on Crystal Falls.

Feb 2019